Tuesday, April 30, 2013

Trusses have arrived

Yesterday, the roof trusses arrived.  These were made in Idaho and trucked directly to Camp Don Harrington.


Happy Scouting!

Monday, April 29, 2013

Kitchen Concrete poured

The Kitchen area has concrete now!  Just a few more things to do and the framers will start.  The Roof Trusses have also arrived.  More photos will be coming soon!


Happy Scouting!

Wednesday, April 17, 2013

Slab Ready for Pouring

The new Dining Hall is beginning to take shape.  The rough plumbing, water, electrical, and gas are done and the slab is ready to be poured.  With the upcoming cold weather, there may be a day or two delay but we are still ahead of schedule.  Construction meetings are now being held every two weeks at the site so the Council (owners), Builder, and the Architects can discuss timelines, concerns, issues etc.  It's already a great partnership with all involved!  Check out the pictures below!

Happy Scouting!


This is a photo of the main Dining Hall floor!
This is a photo of the kitchen and bathroom areas.  The Dining Hall is on the right side of the photo.

Thursday, April 4, 2013

Concrete and Utilities Update

The footings have been poured and the utilities (plumbing, gas, electricity, drains) are being placed.  We expect the slab to be poured mid next week and then within two days, the framers will come.  Check out the pictures below!



Happy Scouting!